通过电磁暂态仿真程序ATP-EMTP,建立了110 kV输电线路的雷击分析模型,主要包括:雷电流模型、杆塔模型、绝缘子串闪络模型等,该模型可以真实地反映雷电流在杆塔上的传播过程.然后分别利用规程法和ATP仿真法进行了计算与分析,得到线路在不同条件下的跳闸率;分析了杆塔高度、冲击接地电阻以及线路绝缘水平等因素对雷击跳闸率的影响.结果表明:在同等情况下,ATP-EMTP仿真计算的反击跳闸率略高于规程法的计算值;随着杆塔高度的降低、杆塔冲击接地电阻的减小、绝缘强度的增强,反击跳闸率减小.
The lightning strike analysis model of 110kV transmission line is established by using the electromagnetic transient simulation program ATP-EMTP,which mainly includes:lightning current model,tower model,and insulator string flashover model,etc.This model can truly reflect the transmission process of lightning current on the tower.The calculation and analysis on the trip rate of the line under different conditions are carried out respectively by using the rule method and ATP simulation method.The influence of the tower height,impulse grounding resistance and line insulation level on the lightning trip out rate is analyzed.The results show that:under the same circumstances,the ATP-EMTP simulation calculation of the counterattack trip rate is slightly higher than the calculation value of the regulation method;with the tower height and the tower impulse grounding resistance decreasing and the insulation strength increasing,the counterattack trip rate decreases.
作者
肖安南
张蔚翔
焦玉平
崔泽宁
郑轶超
朱能富
王欢
XIAO Annan;ZHANG Weixiang;JIAO Yuping;CUI Zening;ZHENG Yichao;ZHU Nengfu;WANG Huan(State Grid Anhui Electric Power Company,Hefei 230000,China;State Grid Anhui Electric Power Research Institute,Hefei 230000,China;State Grid Anhui Electric Power Company Maintenance Branch,Hefei 230000,China;State Grid Anhui Electric Power Company Huainan Power Supply Company,Huainan 232000,China;Anhui South Following Far Grid Technology Co.,Ltd.,Hefei 230000,China)
出处
《电瓷避雷器》
CAS
北大核心
2019年第4期146-150,共5页
Insulators and Surge Arresters
关键词
输电线路
反击
耐雷性能
规程法
ATP-EMTP
transmission line
lightning counterattack
performance
specification
ATP-EMTP