摘要
在工程设计中遇到软土硬壳地基时,一般是进行软土地基加固处理,这样一来就破坏了硬壳层的整体性,延长了工期,增加了造价。对路堤下软土硬壳层地基沉降计算方法进行研究,利用修正后的公式计算试验监测断面的沉降量,并与现场监测数据进行比较,目的是分析直接在软土硬壳层上填筑的路堤的沉降变化。
During the foundation construction of hard shell in soft soil in engineering design,the reinforcement treatment of soft soil foundation is usually performed,which destroys the integrity of hard shell course,prolongs the construction period and increases the cost.The research on the foundation settlement calculation method of hard shell course in soft soil under embankment is made.The settlement of test monitoring section is calculated by using the revised formula and compared with the field monitoring data.The purpose is to analyze the settlement change of embankment directly filled on hard shell course in soft soil.
作者
毛成琦
安泰莹
毛艳蕾
MAO Cheng-qi;AN Tai-ying;MAO Yan-lei(Shanxi Transportation Construction Engineering Quality Inspection Center,Taiyuan 030006,China;Supporting Team of Naval Support Department in Northern War Zone,Qingdao 266001,China;Unit 91206,Qingdao 266108,China)
出处
《北方交通》
2019年第9期55-57,61,共4页
Northern Communications
关键词
路堤
软土硬壳地基
沉降量
Embankment
Hard shell in soft soil foundation
Settlement