结合斯里兰卡Kaluganga水库首部工程实际工程情况,项目部通过混凝土出机口的温度分析,并有针对性对各混凝土原材料采取了一系列的温控措施,使斯里兰卡Kaluganga水库首部混凝土出机口温度能够满足合同技术规范的要求。
Combining with the actual engineering situation of the first project of Kaluganga Reservoir in Sri Lanka,the project department has adopted a series of temperature control measures for concrete raw materials through temperature analysis of concrete outlet,so that the temperature of the first concrete outlet of Kaluganga Reservoir in Sri Lanka can meet the requirements of the technical specifications of the contract.