摘要
为了研究抑制钢轨电位过高的方法,保护信号设备和人员的安全,通过分析钢轨电位产生机理,仿真计算牵引供电和回流通道阻抗,提出了敷设贯通地线并与钢轨等电位连接的防护措施。在西北地区某站的改造试验,验证了防护措施的有效性。
In order to study the method of restraining rail potential from being too high and protect the safety of signal equipment and personnel,this paper analyzes the mechanism of rail potential generation,simulates and calculates the impedance of traction power supply and return channel,and puts forward the protective measures of laying links up grounding wire and equipotential connection with rail.The modifi cation test at a station in Northwest China has verifi ed the effectiveness of the protective measures.
作者
陈静平
沈云山
Chen Jingping;Shen Yunshan
出处
《铁路通信信号工程技术》
2019年第A01期63-65,共3页
Railway Signalling & Communication Engineering
关键词
钢轨电位
贯通地线
等电位连接
rail potential
links up grounding wire,equipotential bonding