以漳州万科城项目为例,结合现场水文地质情况,对深基坑施工前期、施工阶段、开挖等方面的监理要点进行了详细阐述,保证了深基坑支护工程的施工质量。
Taking Zhangzhou Vanke City project as an example, combined with the hydrogeological conditions of the site, this paper expounds the key points of supervision in the early stage, construction stage and excavation of the deep foundation pit construction, so as to ensure the construction quality of the deep foundation pit support project.
作者
吴永璋
Wu Yongzhang(Xiamen Xiangyu Engineering Consulting Management Co.,Ltd.,Xiamen Fujian 361000)
出处
《江西建材》
2019年第10期170-171,共2页
Jiangxi Building Materials
关键词
高层建筑
深基坑支护
工程监理
控制要点
High-rise building
Deep foundation pit support
Engineering supervision
Control points