随着国家大力推行预制装配式建筑,桥梁下部结构的预制拼装技术得到了快速发展。结合无锡市凤翔路快速化改造工程,对盖梁的施工方法进行介绍,通过对比分析各种施工方法的优缺点,最终选取分段式的预制装配式盖梁方案。介绍预制装配盖梁分段方法及详细的拼装流程,总结各步骤中的施工要点。预制装配式盖梁在无锡凤翔路高架桥中的成功应用可为同类工程羞梁结构选型与设计提供参考。
With the vigorous promotion of prefabricated and assembled buildings by the state,the prefabrication and assembly technology of bridge substructure has been rapidly developed.Combined with the expressway renovation project of Wuxi Fengxiang Road,the various construction methods of bent caps are introduced.Through comparative analysis of the advantages and disadvantages of these construction methods,the segmental prefabricated bent cap scheme is finally selected.The prefabricated bent cap segmental method and the detailed assembling process are introduced,and the construction essentials of each step are summarized.The successful application of prefabricated bent caps in Wuxi Fengxiang Road Overpass provides the reference for the selection and design of the bent cap structures in the similar projects.
作者
杨炜
任才
Yang Wei;Ren Cai
出处
《城市道桥与防洪》
2019年第11期121-124,m0014,共5页
Urban Roads Bridges & Flood Control
关键词
城市高架
预制拼装
盖梁
快速施工
分段方案
urban overpass
prefabrication and assembly
bent cap
expressway construction
segmental scheme