摘要
以某地铁车站基坑降水工程为例,说明了工程设计参数、原设计要求、现场实施方案及降水效果,并指出设计文件的不足。针对工程中的问题进行管理责任分析,并提出相应解决措施,为类似工程提供借鉴。
Taking the foundation pit dewatering project of a subway station as an example,the engineering design parameters,original design requirements,on-site implementation plan and precipitation effect are explained,and the shortage of design documents is pointed out. Conduct management responsibility analysis for problems in the project,and propose corresponding solutions to provide reference for similar projects.
作者
丁剑敏
吕化冰
Ding Jian-min;Lyu Hua-bing
出处
《建筑技术开发》
2019年第21期159-160,共2页
Building Technology Development
关键词
危险性较大工程
专家论证内容
工程变更的办理
more dangerous projects
expert argumentation content
handling of engineering changes