摘要 新疆阜康抽水蓄能电站为在建项目,结合项目上库地形、地质以及水文、枢纽布置等条件,确定了以抽排+导流洞导流+管道导流的组合施工导流方案,有效的减少了项目施工期上库导流布置对主体工程的施工干扰。简述了工程上水库施工导流的设计,包括导流标准、导流方式及导流建筑物的设计等,该导流方案不同于以往其他抽蓄项目上库的施工导流方案,对后续类似工程具有极大的借鉴及参考意义。 Xinjiang Fukang pumped storage power station is a project under construction. The article combines the topography,geology,hydrology and hub layout of the project to determine the combined construction diversion of drainage + diversion tunnel diversion + pipeline diversion. The scheme effectively reduces the construction interference of the upper diversion arrangement of the project during the construction period of the project. This paper briefly describes the design of the reservoir construction diversion in the project,including the diversion standard,the diversion method and the design of the diversion building. The diversion scheme is different from the construction diversion scheme of the other reservoirs in the past. Great reference and reference significance for subsequent similar projects.
作者 苏晓军 任小亮 Su Xiaojun;Ren Xiaoliang(Huanghe Hydropower Development Corporation Limited,Xining 810008,China;Power China Northwest Engineering Corporation Limited,Xi’an 710065,China)
出处 《山西建筑》 2019年第22期153-154,共2页 Shanxi Architecture
关键词 抽水蓄能电站 上水库 施工导流 pumped storage power station upper reservoir construction diversion
  • 相关文献

参考文献1

二级参考文献1

  • 1广东省水利电力勘测设计研究院.广东清远抽水蓄能电站可行性研究报告[R].广州:广东省水利电力勘测设计研究院,2007.

共引文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部