期刊文献+

DG水电站枢纽及建筑物设计 被引量:1

Design of the Overall Layout and Main Structures of DG Hydropower Station
下载PDF
导出
摘要 DG水电站坝址区河谷狭窄,上下游分布有崩坡积体和泥石流沟,枢纽布置受地形地质条件限制较大。设计通过坝轴线、枢纽布置格局、筑坝材料等各方面比选,最终确定了碾压混凝土重力坝、左岸溢流坝段、右岸坝后式厂房的枢纽方案。该方案充分利用了坝址现有地形地质条件,总体布置合理、紧凑、开挖量适中、边坡支护工程量省,主要建筑物设计合理。 The overall layout of DG Hydropower Station Project is greatly restricted by the topographical and geological conditions as the river valley is relatively narrow and colluvial deposits and debris flow gullies are found in the project site. After a comparison of several layout schemes considering the dam axis, overall layout and construction materials, a roller compacted concrete gravity dam scheme is selected, in which the overflow dam spillways are built on the left bank monoliths and the behind-dam powerhouses are built behind the right bank monoliths. This layout scheme fully utilizes the favorable topographical and geological conditions of the dam site. The overall layout is compact and reasonable with moderate excavation, less slope support work, and rational design of main structures.
作者 朱瑞晨 姜宏军 杜润宁 吴世勇 沈明 卢乾 李蒋金 ZHU Ruichen;JIANG Hongjun;DU Running;WU Shiyong;SHEN Ming;Lu Qian;LI Jiangjin(Powerchina Huadong Engineering Co.,Ltd.,Hangzhou 311122,China)
出处 《水电与新能源》 2019年第12期1-4,46,共5页 Hydropower and New Energy
关键词 地形地质条件 枢纽布置 碾压混凝土重力坝 主要建筑物设计 水电站 topographic and geological conditions project layout roller compacted concrete gravity dam design of main structures hydropower station
  • 相关文献

参考文献3

二级参考文献3

共引文献9

同被引文献6

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部