DG水电站大坝工程碾压混凝土仓面设计 被引量:4

Design of the Roller Compacted Concrete Pouring Bays of the Dam in DG Hydropower Station
下载PDF
导出
摘要 针对DG水电站坝体碾压混凝土施工组织与系统规划,通过仓面设计--单元工程浇筑前必要的技术准备及指导浇筑作业的一种重要措施,在工程施工中切实发挥了规范施工作业、保证工程质量、加快施工进度的作用,尤其在西藏高海拔地区特殊气候与建设条件极差的情况下更具指导意义。 As a necessary technical preparation before the unit pouring job and an important measure to guide the concrete pouring work, the concrete pouring bay design adopted in the construction organization and system planning of the roller compacted concrete dam in DG Hydropower Station is introduced, which plays a practical role in standardizing the construction work, ensuring the project quality and accelerating the construction progress. It is of great significance especially for the special climate and poor construction conditions in high altitude area of Xizang.
作者 邱冬梅 熊涛 蔡畅 杨卫 QIU Dongmei;XIONG Tao;CAI Chang;YANG Wei(Xizang Construction Engineering Co.,Ltd.,Sinohydro Bureau 9 Co.,Ltd.,Lhasa 850000,China)
出处 《水电与新能源》 2019年第12期12-16,共5页 Hydropower and New Energy
关键词 西藏地区 碾压混凝土 DG水电站 仓面设计 资源规划 Xizang area roller compacted concrete DG Hydropower Station design of pouring bays resource planning
  • 相关文献

参考文献2

共引文献2

同被引文献10

引证文献4

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部