摘要
为缩短锚系安装周期,通过对锚链筒、锚台和锚唇优化设计及安装工序重组,简化安装步骤、降低安装难度,使得分段建造效率得到快速提升。
The integration installation for hawse pipe, anchor bed and lip was achieved well benefit because of less operation combined with lowered difficulty by optimized design of the hawse pipe, anchor bed and lip, and step reorganization of installation. Hence, construction efficiency for the block with anchor fitting was rapidly improved.