天津市第一中心医院新址扩建项目底板混凝土施工技术 被引量:5

Basement Concrete Construction Technology of New Site Expansion Project of Tianjin First Central Hospital
下载PDF
导出
摘要 天津市第一中心医院新址扩建项目筏板基础及主体结构混凝土体量超大,考虑到后浇带极易因处理不当所带来的质量隐患,以及避免对后续施工工序的影响,底板及地下室结构采用跳仓法施工。通过调整分仓尺寸及施工部署,缩短了施工工期,简化了建筑结构设计。地下室结构及施工缝的处理采用纳米防水水泥,保证了工程质量。 The concrete volume of raft foundation and main structure is very large in new central expansion project of Tianjin First Central Hospital. Considering the quality hidden danger caused by improper treatment of post cast strip and avoiding the impact on the subsequent construction process,the sequence construction method is adopted for the construction of bottom slab and basement structure. By adjusting the size of the warehouse and the construction arrangement,the construction period is shortened and the design of the building structure is simplified. The basement structure and construction joints are treated with nanometer waterproof cement to ensure the quality of the project.
作者 孔令宇 杜永奎 商栏柱 左亮 温永刚 KONG Lingyu;DU Yongkui;SHANG Lanzhu;ZUO Liang;WEN Yonggang(China Construction Third Engineering Bureau Co.,Ltd.,Wuhan,Hubei 430064,China)
出处 《施工技术》 CAS 2019年第22期76-79,共4页 Construction Technology
基金 中建三局与天津大学联合科研课题
关键词 混凝土 跳仓法 膨胀加强带 纳米防水水泥 施工技术 concrete sequence construction method expansion reinforcing band nanometer waterproof cement construction
  • 相关文献

参考文献4

二级参考文献18

共引文献35

同被引文献30

引证文献5

二级引证文献28

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部