摘要 在论述吊装影响因素的基础上,对新型半潜式起重平台吊装流程进行设计和规划:受主机功率的限制,在起吊过程中快速排出压载水以满足货物脱离速度的要求;鉴于双吊联合回转的复杂性,构建该过程限制条件的数学模型,并开发用于确定吊机联动作业的优化程序。以某Spar平台上部模块吊装为例,通过优化求解获得吊臂最佳初始提升角和两吊机回转过程,并应用时域模拟来获得吊物详细运动和关键节点视图,以验证优化程序的可靠性。 On the basis of discussing the influencing factors of hoisting,the platform hoisting process is designed.In view of the limitation of the main engine power,the ballast water is quickly discharged during the hoisting process to meet the requirements of escape velocity of the cargo.In view of the complexity of the double hanging simultaneous slewing,a mathematical model of the process constraints is constructed,and an optimization program for determining the simultaneous operation of the crane is developed.Taken the hoisting process of superstructure module of a Spar platform as an example,the optimal initial hoisting angle of the boom and the slewing process of the two cranes are obtained through optimization.Time domain simulation is applied to obtain the motion and key node views of the cargo to verify the reliability of the optimizer.
作者 王金光 徐立新 胡琦 Zhou Joe 黄凯 Datta Indra WANG Jinguang;XU Lixin;HU Qi;ZHOU Joe;HUANG Kai;DATTA Indra(China Merchants Offshore Technology Research Center,Nantong 226116,Jiangsu,China;OOS International B.V.,Serooskerke,Zeeland 4353ZG,Netherland)
出处 《中国海洋平台》 2019年第6期5-9,共5页 China offshore Platform
关键词 半潜式起重平台 联合吊装 联动作业 过程优化 时域模拟 Semi Submersible Crane Vessel(SSCV) tandem hoisting simultaneous operation process optimization time domain simulation
  • 相关文献

参考文献3

二级参考文献20

  • 1Ayman B M, Hussein W EI-Tahan. On the use of the capability polar plots program for dynamic positioning systems for marine vessels[J]. Ocean Engineering 33 (2006) 1070-1089.
  • 2DET NORSKE VERITAS,RULES FOR CLASSIFICATION OF SHIPS,PART 6 CHAPTER 7. 2004.
  • 3Faltinsen O M. Sea Loads on Ships and Offshore Structures. Cambridge University Press. 1999.
  • 4API-RP-2SK. Design and Analysis of Stationkeeping Systems for Floating Structures[M]. 2005.
  • 5Recommended Practice DNV-RP-C205[M]. Environmental Conditions and Environmental Loads. 2007.
  • 6BOMEL Ltd. Decommissioning topic strategy for the Health and Safety Executive, P. 49. OFFSHORE TECHNOLOGY REPORT, 2001/032.
  • 7William Cash, Dual barge-truss system aims at 20,000-ton lift, Versatruss Americans L. L. C.
  • 8The Pioneering Years 1960 - 1978 of Heerema. http://www. heerema. com/
  • 9Gertjan Looye, Instruction to S. S. C. V, http://www.offshore-vessels.net/
  • 10Eni Group, Saipem 7000, http://www. saipem. eni. it/

共引文献25

同被引文献16

引证文献3

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部