几内亚苏阿皮蒂大坝碾压混凝土入仓方式的研究与运用 被引量:3

Research and Application of Roller Compacted Concrete Placing Method in Souapiti Dam of Guinea
下载PDF
导出
摘要 几内亚苏阿皮蒂水利枢纽工程碾压混凝土重力坝混凝土浇筑总量约360万m 3,合同工期58个月,其中混凝土浇筑高峰期在2018年~2019年,混凝土月高峰强度超过20万m 3。介绍了苏阿皮蒂大坝碾压混凝土的入仓方式,合理的混凝土入仓方案保证了工程的顺利建设,为水电站在2020年按期发电和完工奠定了良好的基础。 The total amount of concrete for the RCC gravity dam of Souapiti Hydro Project is about 3.6 million m 3.The contracted concrete pouring period is 58 months,in which,the peak period of concrete pouring is between 2018 and 2019 with a peak intensity of more than 200 thousand m 3.The concrete placing method for the RCC dam of Souapiti Hydro Project is introduced.The reasonable concrete placing scheme ensures the smooth construction of project and lays a good foundation for the hydropower station to generate electricity and complete on schedule in 2020.
作者 王以斌 寿开 刘玉琴 李全旭 WANG Yibin;SHOU Kai;LIU Yuqin;LI Quanxu(China International Water&Electric Corp.,Beijing 100120,China)
出处 《水力发电》 北大核心 2020年第1期81-85,共5页 Water Power
关键词 碾压混凝土 入仓道路 苏阿皮蒂水利枢纽 几内亚 roller compacted concrete road for concrete placing Souapiti Hydro Project Guinea
  • 相关文献

同被引文献34

引证文献3

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部