哈尔乌素露天煤矿首采区端帮运输系统优化 被引量:4

Optimization of end slope transportation system in first mining area of Har’erwusu Open-pit Mine
下载PDF
导出
摘要 为解决哈尔乌素露天煤矿端帮运输系统布置与生产实际日益不匹配,剥采重心失调的问题,结合具体地质勘探资料,以综合运距、边坡稳定性系数、长期适用性为考量,对多个端帮运输设计方案进行比选,进而得到最优技术方案。结果表明:优化方案消减了哈尔乌素露天煤矿边坡安全隐患,显著地降低了不必要的运输费用。 In order to solve the mismatched problem of the arrangement and production practice of the end slope transportation system in Har’erwusu Open-pit Mine, combining with specific geological exploration data, considering the comprehensive transportation distance, slope stability coefficient and long-term applicability, we select multiple design schemes to obtain the optimal technical solution. The results show that the optimization scheme reduces the safety hazard of the slope of Har’erwusu Open-pit Mine and significantly reduces the unnecessary transportation costs.
作者 韩占占 张禹 HAN Zhanzhan;ZHANG Yu(China Energy Investment Group Shenhua Har'erwusu Open-pit Mine,Ordos 010300,China)
出处 《露天采矿技术》 CAS 2019年第6期60-63,共4页 Opencast Mining Technology
关键词 露天矿 运输系统 边坡 运距 剥采重心失调 open-pit mine transportation system slope transportation distance stripping mining imbalance
  • 相关文献

参考文献7

二级参考文献29

共引文献65

同被引文献26

引证文献4

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部