摘要
本文以某型82000DWT散货船分段划分为基础,结合实际情况,分别对双层底、舷侧、首部、舵机舱及尾部、上建等5个预总段及总段进行设计优化。依据优化后的预总段及总段划分方法,可有效提高舱室结构及舾装完整性,减少压载舱区域涂层因后续施工引起的破坏,同时缩短总段总组及搭载周期。
Based on the block division of an 82000DWT bulk carrier,combined with the actual situation,the design optimization of the prefabricated blocks and blocks including double bottom,side,bow,steering engine room,stern and superstructure are carried out respectively.According to the optimized prefabricated block and block division method,the integrity of cabin structure and outfitting can be effectively improved,the damage of the coating in the ballast tank area caused by the subsequent construction can be reduced,and the cycle of block assembly and erection can be shortened.
作者
袁辉
YUAN Hui(Hudong-Zhonghua Shipbuilding(Group)Co.,Ltd.,Shanghai 201913)
出处
《广东造船》
2019年第6期58-60,77,共4页
Guangdong shipbuilding