摘要
冬期施工已不乏其例,但国内在高寒地区进行预制梁冬期施工的成功案例比较少。通过对青海省德令哈制梁场冬期制梁施工的总结,研究原材料、混凝土搅拌、混凝土灌注、梁体养护的加热和保温措施,提出了后期配套措施的保温等问题,获得了一套在高寒地区现场预制梁的冬期施工技术。
There are many cases of winter construction,but there are not many successful cases of winter construction of prefabricated beams in alpine-cold region. Based on the summary of the winter beam-making construction in Delingha Beam-making Works,this paper studies the heating and heat preservation measures of raw materials,concrete mixing,concrete pouring and beam body maintenance,puts forward the heat preservation problems of the later supporting measures,and obtains a set of winter construction technology of field prefabricated beams in alpine-cold region.
作者
王新建
WANG Xin-jian(Sinorex Resource&Environment Engineering(Beijing)Co.,Ltd,Beijing 100012)
出处
《矿产勘查》
2019年第11期2843-2849,共7页
Mineral Exploration
关键词
高寒地区
冬期施工
预制梁
alpine-cold region
winter construction
precast beam