不同张拉顺序下的斜拉桥施工索力分析 被引量:8

Cable force analysis of cable-stayed bridges under different tension sequences
下载PDF
导出
摘要 在斜拉桥施工中,因施工条件有限导致拉索张拉顺序的改变,其施工索力也随之改变。通过差值法分析西北高原上某独塔非对称斜拉桥,比较不同张拉顺序下拉索的施工索力,结果表明:改变张拉顺序后,对一张力影响较小,对二张力影响较大,对实际工程有一定参考意义。 In the construction of cable-stayed bridges,due to the limited construction conditions,the tensioning sequence of the cable changes,and the construction cable force also changes. Through the difference method,a single tower asymmetric crossstayed bridge on the northwestern plateau of China is analyzed to compare the cable tension of the tension cables in different sequences. The results show that after changing the tension sequence,the cable tension of the first tension construction is less affected,the impact on the cable tension of the second tension construction is large. There are certain reference significance to practical engineering.
作者 杨雄 Yang Xiong(College of Civil Engineering,Lanzhou Jiaotong University,Lanzhou 730070,China)
出处 《山西建筑》 2020年第3期132-134,共3页 Shanxi Architecture
关键词 斜拉桥 张拉顺序 施工索力 cable-stayed bridge tensioning sequence construction cable tension
  • 相关文献

参考文献3

二级参考文献10

共引文献25

同被引文献49

引证文献8

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部