摘要
小断面土洞段贯通实施方案,即贯通段一端采用超前水平高压旋喷桩结合超前帷幕注浆的开挖支护方式,另一端采用三台阶开挖、超前大管棚及注浆支护的方式。通过对山西省小浪底引黄工程某项目的土洞贯通方案进行详细阐述,提出基于两端开挖支护方式下实现隧洞贯通及贯通过程中的安全控制措施。
Small section soil tunnel section through-hole implementation plan,that is,one end of the through-section adopts advanced horizontal high-pressure rotary jet grouting combined with advanced curtain grouting and excavation,and the other end adopts three-step excavation,large pipe shed and grouting the way.Through detailed explanation of the tunnel penetration scheme of a project in the Xiaolangdi Yellow River Diversion Project in Shanxi Province,safety control measures for tunnel penetration and penetration are proposed based on the excavation and support at both ends.
作者
鲁西西
杨帅
黄怡锋
Lu Xixi;Yang Shuai;Huang Yifeng(Xiaolangdi Yellow River Diversion Project Construction Administration in Shanxi Province,Taiyuan 030002,Shanxi;Shanxi Xiaolangdi Yellow River Diversion Engineering Co.,Ltd.,Taiyuan 030002,Shanxi)
出处
《陕西水利》
2019年第12期7-9,共3页
Shaanxi Water Resources
关键词
土洞
超前水平旋喷
超前帷幕注浆
超前大管棚注浆
贯通
Soil cave
advanced horizontal rotary jetting
advanced curtain grouting
advanced large pipe shed grouting and penetration