摘要
依据现行的国家及行业标准、规范,介绍了输油气管道与光缆同沟直埋敷设的设计、施工的做法及施工步骤;结合涪陵页岩气田焦石坝区块一期产能建设中输气管道与光缆同沟直埋在山区地段敷设的工程实践,指出了在山区地段同沟直埋施工的困难及存在的问题,对实用性进行了探讨,并提出解决方案,对今后类似的输气管道与光缆同沟直埋敷设工程具有一定的借鉴作用。
According to the current national and industrial standards and specifications, this paper introduces the design, construction method and construction steps of directly buried and laid oil and gas pipelines and optical cables in the same trench. Based on the engineering practice of directly burying gas pipeline and optical cable in mountainous area in the first stage productivity construction of Jiaoshiba block in Fuling shale gas field, this paper points out the difficulties and existing problems in the construction of the same trench in mountainous area, probes into the practicability, and puts forward some solutions, which can be used for reference to the similar direct buried project of gas pipeline and optical cable in the future.
作者
孙必川
Sun Bichuan(SINOPEC Energy and Environmental Engineering CO.,LTD,Wuhan 430223)
出处
《石化技术》
CAS
2020年第1期62-64,共3页
Petrochemical Industry Technology
关键词
光缆
输气管道
山区地段
同沟敷设
设计
施工
存在问题
实用性
解决方案
Fibre Optical Cable
Gas pipeline
Mountainous areas
Laid in the same trench
Design
construction
Open question
Practicability
solution Plan