基于FLAC3D隧道超前孔卸压影响范围研究 被引量:3

Study on Influence Range of Pressure Relief of Advance Drilling in Tunnel Based on FLAC3D
下载PDF
导出
摘要 针对西藏某隧道因花岗岩、片麻岩在高地应力条件下因围岩应力过大导致双护盾TBM开挖困难的实际情况,考虑采用超前钻孔卸压的方式使围岩应力减小以方便开挖,对超前钻孔影响的范围进行了研究。阐述了通过FLAC3D对超前钻孔进行数值模拟,对超前孔卸压影响范围进行分析的过程,得出超前孔对围岩压力影响的范围是其钻孔半径的5~6倍的结论。研究得出的超前孔卸压的影响范围,可为今后西藏高地应力条件下的TBM施工提供借鉴。 In view of the fact that it is difficult to excavate by double shield TBM due to the high ground stress of granite and gneiss in a tunnel in Tibet,the way of pressure relief in advance drilling is considered to reduce the stress in the surrounding rock to facilitate the excavation,and the influence range of advance drilling is studied.This paper describes the process of numerical simulation of advance drilling by FLAC3D and analysis of the influence range of pressure relief of advance drilling,it is found that the influence range of the advance drilling on the surrounding rock pressure is 5-6 times of its drilling radius.The influence range of the pressure relief of the advance drilling can be used for reference for the TBM construction in Tibet or under the conditions of high ground stress in the future.
作者 徐应中 文俊 李超 陈秉政 XU Yingzhong;WEN Jun;CHENG Jinzhong(Sinohydro Bureau 10 Co.,Ltd,Chengdu,Sichuan,610072;College of Environment and Civil Engineering,Chengdu University of Technology,Chengdu,Sichuan,610059)
出处 《四川水力发电》 2020年第1期63-65,72,共4页 Sichuan Hydropower
关键词 超前钻孔 双护盾TBM 高地应力 FLAC3D 数值模拟 advance drilling double shield TBM high ground stress FLAC3D numerical simulation
  • 相关文献

参考文献5

二级参考文献31

共引文献14

同被引文献46

引证文献3

二级引证文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部