摘要 事实证明,随着大坝填筑量上升,料场富余系数就越大,因此,可将料场中下部开挖坡比放缓,减少支护工程量,甚至可以不支护。针对高山峡谷区工程地质性状极差的强卸荷带内松动岩带,因地制宜地以极少的代价采取清除及绕避办法成功地进行了处理。最终确保了块石料场边坡稳定和施工安全,使大坝填筑提前6个月完成,又大大节约了支护工程量。 It has been proved that with the increase quantity of dam filling,the allowance coefficient of the quarry will be larger.Therefore,the excavation slope ratio of the middle and lower part of the quarry can be reduced so that the amount of support works can be reduced,or even no support can be provided.In view of the loose rock zone in the strong unloading zone with poor engineering geological properties in the high mountain canyon area,the removal and avoidance methods were successfully carried out at a very low cost in accordance with local conditions.Finally,the slope stability and construction safety of the quarry are ensured,the dam filling is completed 6 months in advance,and the support work quantity is greatly saved.
作者 杨国华 冯文新 胡金山 YANG Guohua;FENG Wenxin;HU Jinshan(Henan Geology Mineral College,Zhengzhou,Henan,450000;Chengdu Engineering Co.,Ltd,Power China,Chengdu,Sichuan,610072)
出处 《四川水力发电》 2020年第1期107-110,共4页 Sichuan Hydropower
关键词 超高土石坝 料场边坡 勘察设计 动态调整 super high earth-rock dam quarry slope survey and design dynamic adjustment
  • 相关文献

参考文献3

二级参考文献10

  • 1东北地震监测研究中心(译),活动构造与工程选址论文集,1991年
  • 2丁国瑜,中国岩石动力学概论,1991年
  • 3李兴唐,区域地表稳定性研究理论与方法,1987年
  • 4水利水电部水利水电规划设计院,水利水电工程地质手册,1985年
  • 5孙广忠,岩体力学基础,1983年
  • 6韩文峰,黄河黑山峡小观音坝址工程地质研究,1999年
  • 7韩文峰,黄河黑山峡大柳树松动岩体工程地质研究,1993年
  • 8彭进夫,水力发电,1992年,1期,7页
  • 9Li Jijun,Quaternaxy Science Reviews,1991年,10卷,479页
  • 10胡金山,凡亚,闵勇章,刘永波,曹建平.“超高砾石土石心墙坝防渗土料勘察与确定方法(以长河坝水电站为例)”.高坝建设与运行管理的技术进展(中国大坝协会2014学术年会论文集)[c].郑州:黄河水利出版社,2014:592-599.