核电厂安全重要物项的分级识别概述

Review of Categorizing and Identifying Structures,Systems,and Components in NPPS According to Their Safety Significance
下载PDF
导出
摘要 论文介绍了国内核安全法规和现有标准中基于确定论方法的核电厂安全相关物项分级方法,以及美国核电领域基于风险指引的安全重要物项分级和筛选识别方法。通过美国核电厂基于风险指引物项分级的应用实例,说明开展安全重要物项分级的意义和必要性。 This paper introduces the categorization method of safety-related SSCs based on deterministic method in China's nuclear safety regulations and standards,and introduces the risk-informed categorization and identification methods for safety-significant SSCs in the U.S.nuclear power field.This paper illustrates the significance and necessity of developing risk-informed categorization,through the example of the application of this categorization method in the US nuclear power plants.
作者 邱春辉 顾剑峰 马静娴 宋强 谭坤 QIU Chun-Hui;GU Jian-Feng;MA Jing-Xian;SONG Qiang;TAN Kun(China Productivity Center for Machinery,Beijing 100044,China)
出处 《机电产品开发与创新》 2020年第1期49-51,共3页 Development & Innovation of Machinery & Electrical Products
基金 大型先进压水堆核电站重大专项中国先进核电标准体系研究(第二阶段)项目(2017ZX06004001)
关键词 物项分级 风险指引 安全重要 SSCs categorization risk-informed safety significance
  • 相关文献

参考文献1

二级参考文献10

  • 110CFR50.69.Section 50.69 Draft Rule Language[S].
  • 2NEI-00-04 (DRAFT-Final Draft R2).10 CFR 50.69 SSC Categorization Guideline[S].
  • 3C.R.GRANTOM.P.E.PSA Techniques in component risk significance categorization[C]//Use of PSA in Operation of NPPs and in Regulatory Decision-Making.Kyia,Ukraine,2004.
  • 4BROWN J A,OSTERRIEDER R A,LUTZ R J,et al.Westinghouse owners group risk-informed regulation efforts-Option 2 and 3[C]//Proceedings of ICONE 10,Arlington,Virginia,USA,2002.
  • 5RG 1.200.An approach for determining the technical adequacy of probabilistic risk assessment results for Risk-Informed activities[S].
  • 6ASME standard for probabilistic risk assessment for nuclear power plant applications.(Rev.14A.)[S].
  • 7NEI-00-02.probabilistic risk assessment(PRA) peer review process guidance[S].
  • 8UCHIDAT.The trial identification of safety significant components with risk importance measures[C].//The 8th Japan-Korea PSA Workshop,Tokyo,Japan,2004.
  • 9BROOK K.The use of risk informed decision making in the operation of sizewell B[C]// The Application of Probabilistic Safety Analysis,Cape Town,South Africa,2002.
  • 10DAEIL KANG. Pilot study on the applications of risk-informed in-service testing method to check valves for ulchin unit 3[C]// The 7th Korea-Japan PSA Workshop, Jeju-lsland, Korea, 2002.