大红山铜矿胶结矿柱稳定性数值模拟研究 被引量:1

Numerical Simulation of Stability of Cemented Pillar in Dahongshan Copper Mine
下载PDF
导出
摘要 在大红山铜矿两步骤连续开采过程中,胶结矿柱将代替原生矿柱服务相邻矿房开采。基于二步骤回采过程的安全性以及稳定性要求,需对一步骤胶结矿柱稳定性分析研究。以385中段B12-20线区域为研究对象,通过FLAC3D软件进行数值模拟研究,结果表明:385中段B12-20线开采区域胶结矿柱能够保证其自身稳定性,不会发生失稳破坏,为区段回采提供了安全可靠的作业环境。 In the two-step continuous mining process of Dahongshan Copper Mine,cemented pillars will replace primary pillars to serve the mining of adjacent mine houses.In order to ensure the safety of the two-step mining process,it is necessary to study and analyze the stability of cemented pillars.Taking the B12-20 line mining area in the middle section of 385 as the research object,the numerical simulation research is carried out by FLAC3D software.The results show that the cemented pillar in the B12-20 line mining area in the middle section of 385 can ensure its own stability without instability and damage,thus providing a safe and reliable working environment for mining in the section.
作者 阮中华 张希 黄飞 RUAN Zhong-hua;ZHANG Xi;HUANG Fei(Yunnan Copper Co.,Ltd.,Kunming 650000,China;Yuxi MiningCo.,Ltd.,Yuxi 651300,China;Faculty of Land Resource Engineering of KUST,Kunming 650000,China)
出处 《价值工程》 2020年第5期206-210,共5页 Value Engineering
关键词 空场嗣后充填采矿法 胶结矿柱 稳定性分析 数值模拟 open field subsequent filling method cemented pillar stability analysis numerical simulation
  • 相关文献

参考文献8

二级参考文献66

共引文献178

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部