本钢高炉停炉操作实践

Process Practice of Blowing Down in Benxi Steel BF
原文传递
导出
摘要 对本钢7号高炉停炉操作实践进行了总结。通过停炉前对炉料负荷的调整和炉顶设备的改进,打水控料位中对风量、顶温和出铁时间等参数的合理控制,共用时22h40min成功将料位降至风口以下,停炉后用时11h41min将炉缸残铁快速放出,实现了安全顺利停炉,为今后高炉大修提供宝贵经验。 Summarized the practice summary of Benxi Steel’s No. 7 blast furnace blow down operation.Adjustment of coke load and improvement of top equipment before stopping the furnace,and reasonable control of parameters such as air volume,top temperature and tapping time in reduce the ore level process,The material level was successfully reduced to below the tuyere in 22 h40 min. After the furnace is shut down,the residual iron in the furnace is quickly released in 11 h41 min. Achieved safe and smooth shutdown,providing valuable experience for future blast furnace overhaul.
作者 李永强 秦希黎 韩廷全 梁科 Li Yongqiang;Qin Xili;Han Tingquan;Liang Ke(The Ironworks of Benxi Steel and Iron Group,Benxi 117000;The Steelworks of Benxi Steel and Iron Group,Benxi 117000)
出处 《冶金设备》 2019年第6期72-75,共4页 Metallurgical Equipment
关键词 高炉 停炉 控料位 冷却壁 BF Blowing down Cooling wall Reduce the ore level
  • 相关文献

参考文献5

二级参考文献10

共引文献22

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部