为提高深基坑工程支护措施,以阜阳市某深基坑工程为实例,根据工程的现场情况选择适合且经济安全的支护方法.通过软件模拟来研究复合土钉墙支护在基坑开挖中带来的影响效果,可为类似工程提供参考.
In order to improve the deep foundation pit engineering support measures,a deep foundation pit engineering in Fuyang City was taken as an example.According to site condition,a suitable engineering and economic security support method were chosen.Through the software simulation,the effect of the composite soil nailing wall in foundation pit excavation was studied.The study can provide some reference for future similar projects.
作者
王春
WANG Chun(College of Civil Engineering,Anhui Jianzhu University,Hefei 230601,China)
出处
《兰州工业学院学报》
2020年第1期53-56,共4页
Journal of Lanzhou Institute of Technology
关键词
复合土钉墙
深基坑工程
有限元分析
composite soil nailing wall
deep foundation pit engineering
finite element analysis