大直径盾构隧道全预制结构拼装技术实践 被引量:19

The Practice of Fully-prefabricated Construction in Large-Diameter Shield Tunnels
下载PDF
导出
摘要 京张高铁清华园隧道是国内首座全预制拼装铁路盾构隧道,包括管片衬砌、轨下箱涵结构及附属结构均实现了工厂化预制,机械化拼装工艺。轨下结构全预制拼装工艺不但加快了施工进度,节约工期,免了大量植筋,提高结构了耐久性,而且还大幅度改善了施工作业环境。介绍轨下全预制结构的设计及施工技术创新应用,通过对现场的拼装错缝统计,分析得出箱涵拼装机无预紧功能,预制件间无螺栓连接、密封材料及施工精度低等因素是产生拼装误差的直接原因。提出采用微膨胀525快硬型硫铝酸盐水泥浆填充预制结构缝隙的改进措施,并采用数值模拟计算分析该方案可靠性与稳定性,结果表明:注浆填充施工误差缝隙后,结构的稳定性及长期运营的安全性均显著提高。 The Tsinghuayuan Tunnel on the Beijing-Zhangjiakou High-speed Railway is China’s first shield tunnel constructed by fully-prefabricated assembling technology.Tunnel lining segments and sub-structures are all prefabricated and mechanically assembled,which not only speeds up the construction progress,improves the durability of the structure,but also greatly improves construction environment.This paper introduces the design and innovative application of the fully-prefabricated construction.The analysis of rail joints concludes that the causes of assembly errors are the failure of the erecting robot to pre-tighten sub-structures,no bolted joint between the prefabricated parts,sealing material and low precision construction.The paper also provides an improvement measure to fill the gaps in prefabricated structure with 525 Sulfoaluminate cement slurry.The results show that after filling the gaps,the security of long-term operations of the shield tunnels has been significantly improved.
作者 张宇宁 岳岭 刘方 吕刚 凌云鹏 ZHANG Yuning;YUE Ling;LIU Fang;LU Gang;LING Yunpeng(China Railway Engineering Design and Consulting Group Co.,Ltd,Beijing 100055,China)
出处 《铁道标准设计》 北大核心 2020年第1期147-152,共6页 Railway Standard Design
基金 中国铁路总公司科技研究开发计划重大课题(2017G007-B)
关键词 高速铁路 铁路隧道 盾构隧道 全预制拼装技术 轨下结构 拼装误差 注浆 high-speed railway railway tunnel shield tunnel fully-prefabricated construction assembling sub-rail structure assembling error grouting
  • 相关文献

参考文献19

二级参考文献167

共引文献796

同被引文献155

引证文献19

二级引证文献40

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部