摘要
南通紫琅公园工程规划面积约2.02×10^6m^,山体堆填区域面积约1.2×10^5m^2,山体堆高0~23m,结合场地的地质条件,对影响堆山的稳定性因素进行深度分析,为不增加大量地基加固费用,最终提出了盲沟排水增加堆山稳定性的天然地基堆筑方法,并总结了保证堆山安全性的施工与监测要点,为类似工程提供参考。
The planning area of Zilang park project in Nantong is about 2.02×10^6 m^2, mountain landfill area is about 1.2×10^5 m^2, the mountain is 0~23 m high. Combined with the geological conditions of the site, the factors influencing the stability of the mounds were deeply analyzed. In order not to increase a large amount of foundation reinforcement cost, a method of natural foundation piling was proposed to increase the stability of mounds by blind ditch drainage, and the key points of construction and monitoring to ensure the safety of mounds were summarized to provide reference for similar projects.
作者
郑志龙
ZHENG Zhi-long(Shanghai Gardens Group Co.Ltd.,Shanghai 200011,China)
出处
《工程建设与设计》
2020年第2期11-14,共4页
Construction & Design for Engineering
关键词
堆山
土方堆筑
监测
piled mountain
earth heap
monitoring