多形式液压爬模在卡普特项目中的应用 被引量:2

Application of Multi Form Hydraulic Climbing Formwork in Kaput Project
下载PDF
导出
摘要 以迪拜卡普特项目为例,阐述了多形式液压爬模技术的应用,在该项目的具体施工中,经过计算机有限元计算分析,多形式液压爬模技术的应用,使其架体结构有效满足了各种工况承载力和不同核心筒结构形状的要求。有效解决了施工中钢板剪力墙、大尺寸伸臂桁架及高层大的施工难度,值得其他类似工程大力参考借鉴。 Based on the specific case of Kaput project in Dubai,the multi-form hydraulic climbing formwork technology is introduced.By computer finite element calculation and analysis,the frame structure effectively meets the requirements of bearing capacity under various working conditions and different core tube structure shapes.The technology can effectively solve the construction difficulties of steel plate shear wall,large-scale boom truss and high-rise building,and it can work as reference for other similar projects.
作者 高凯飞 GAO Kai-fei(International Corporation of CR18G,Tianjin 300350,China)
出处 《浙江水利水电学院学报》 2020年第1期63-67,86,共6页 Journal of Zhejiang University of Water Resources and Electric Power
关键词 多形式 液压爬模 企业大厦 有限元 multiform hydraulic climbing formwork enterprise building finite element
  • 相关文献

参考文献9

二级参考文献40

共引文献56

同被引文献16

引证文献2

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部