摘要
基坑工程施工条件复杂、施工质量要求高,是工程项目施工全过程的核心环节。为了有效地解决某电视中心项目深基坑的全过程施工难题,确保现场施工高效有序进行,本文通过对该深基坑建立BIM参数化三维模型,进行三维场地布置和工程量计算,最后把模型导入Navisworks中进行施工可视化模拟以论证基坑施工方案的可行性。结果表明,引用BIM技术能有效地辅助解决该基坑工程的施工难题,辅助优化施工方案,保证了深基坑现场施工高效有序进行。
With complex construction condition and high construction quality request,the foundation pit engineering is the core of the entire process of project construction.In order to effectively solve the construction problems during the whole process of deep foundation pit construction of a certain TV center project,and to ensure efficient and orderly construction on site,this paper establishes a 3D parametric BIM model of the deep foundation pit for the 3D site layout arrangement and engineering quantity statistics.The model is finally inserted into Navisworks for visualized simulation of construction progress to demonstrating the feasibility of foundation pit construction scheme.The results show that the application of BIM technology will effectively solve the construction problems of the foundation pit project,and assists in optimizing the construction scheme,which ensures the efficient and orderly construction of the deep foundation pit site.
作者
陈燕安
王荣
廖羚
钟超瑜
赖溯欣
赵婕
Chen Yan′an;Wang Rong;Liao Ling;Zhong Chaoyu;Lai Suxin;Zhao Jie(School of Civil Engineering and Architecture,Guangxi University of Science and Technology,Liuzhou 545006,China;Building Information Modeling Research Center,Guangxi University of Science and Technology,Liuzhou 545006,China;Guangxi Construction Engineering Group No.3 Construction Engineering Co.,Ltd.,Liuzhou 545002,China)
出处
《土木建筑工程信息技术》
2020年第1期39-45,共7页
Journal of Information Technology in Civil Engineering and Architecture
基金
2018~2020年度广西本科高校特色专业及实验实训教学基地(中心)建设项目(项目编号:63,特色专业名称:广西科技大学工程管理专业)
国家自然科学基金项目(项目编号:51568008)
广西高校科学技术研究项目(项目编号:KY2015YB164)
教育部高等教育司2018年第二批产学合作协同育人项目(项目编号:201802102016
201802142013
201802276027
201802276028
201802331028)
2015年广西高等教育本科教学改革工程项目(项目编号:2015JGB277)。