期刊文献+

ASME喷嘴垂直安装方式下传压管高差修正的研究

Study on height difference correction of pressure transmission tube under vertical installation of ASME nozzle
下载PDF
导出
摘要 阐述了ASME喷嘴的安装位置及布置方式,并针对各类型电厂性能试验中的主要水流量测量修正问题,比较分析了ASME PTC6、ASME PTC46、ASME PTC6.2三种试验规程中传压管高差修正不一致的情况。对ASME喷嘴垂直安装方式下传压管高差修正做了详细推导,列举了计算中容易出错的两种情况,比较了不同计算方式对电厂经济性的影响,得出了不同计算方式对机组供电煤耗影响数据。 The installation position and layout of ASME nozzles are introduced.Aiming at the main water flow measurement and correction problems in performance tests of various types of power plants,the inconsistencies of the height difference correction of pressure transmission tubes in three test procedures of ASME PTC6,ASME PTC46 and ASME PTC6.2 are compared and analyzed.The correction of the height difference of pressure transmission tubes under vertical installation mode of ASME nozzle is deduced in detail.Two cases of error-prone calculation are enumerated,the effects of different calculation methods on the economy of power plants are compared,and the influence data of different calculation methods on the power supply coal consumption of the unit are obtained.
作者 杨志行 富学斌 府冬明 王宝森 杨光辉 YANG Zhihang;FU Xuebin;FU Dongming;WANG Baosen;YANG Guanghui(State Grid Heilongjiang Electric Power Co.,Ltd.Electric Power Research Institute,Harbin 150030,China)
出处 《黑龙江电力》 CAS 2019年第6期535-537,541,共4页 Heilongjiang Electric Power
关键词 高差修正 喷嘴 ASME 汽轮机性能试验 height difference correction nozzle ASME turbine performance test
  • 相关文献

参考文献1

二级参考文献2

共引文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部