摘要
大断面隧道施工中因地质、工艺等多方面因素易引发坍塌事故。文章以大断面公路黄土隧道工程为例,针对其开挖施工中出现的坍塌问题展开探讨,总结成因并提出可行的防治措施,取得了良好的防治效果。
In the construction of large section tunnels,collapse accidents are likely to be caused by many factors such as geology and technology.The article takes the large section highway loess tunnel project as an example,discusses the collapse problem in its excavation construction,summarizes the causes and proposes feasible control measures,and has achieved good control effects.
作者
王洪奎
WANG Hongkui(China Railway 11th Bureau Group Fourth Engineering Co.,Ltd,Wuhan 441300,China)
关键词
大断面黄土隧道
隧道坍塌
开挖施工
large section loess tunnel
tunnel collapse
excavation construction