深基坑肋墙换撑施工技术 被引量:2

Construction Technology of Support Replacement by Rib Wall in Deep Foundation Pit
下载PDF
导出
摘要 在城市核心区深基坑施工过程中,由于重要社会活动、春节、重大交通管制等原因,容易造成基坑底板封闭时间超时,进而对周边环境与基坑安全产生严重影响。针对上述问题,在上海市某地下4层深基坑分坑施工过程中,采用了一种在基坑内设置肋墙换撑的施工技术,在Ⅰ区分坑施工至地下室中楼板后,提前开挖相邻Ⅱ区分坑的2层土方,使得相邻分坑的底板封闭时间与春节错开,满足了保护周边环境及压缩工期的要求。 During the deep foundation pit construction in urban core area, due to important social activities, Spring Festival, major traffic control and other reasons, it is easy to cause the foundation pit floor closing time to exceed, which will have a serious impact on the surrounding environment and the safety of the foundation pit. In view of the above problems, in the process of pit division construction of a 4-story underground deep foundation pit in Shanghai, a construction technology of setting rib wall in the foundation pit to replace support is adopted. After the construction of division I pit to the middle floor in the basement, two layers of earthwork of the adjacent division II pit are excavated in advance, so that the closing time of the floor of the adjacent divisions is staggered with the Spring Festival, which meets the requirements of protecting the surrounding environment and shortening the construction period.
作者 周圣平 邱承双 周嘉斌 余爱敏 孙宇轩 ZHOU Shengping;QIU Chengshuang;ZHOU Jiabin;YU Aimin;SUN Yuxuan(China Construction Third Engineering Bureau Co.,Ltd.(Shanghai),Shanghai 200129,China)
出处 《建筑施工》 2020年第3期329-331,共3页 Building Construction
关键词 深基坑 分坑施工 中隔墙 肋墙换撑 压缩工期 deep foundation pit pit division construction middle partition wall support replacement by rib wall shortening construction period
  • 相关文献

参考文献6

二级参考文献22

共引文献121

同被引文献23

引证文献2

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部