摘要
沙特朱拜勒海滨公园项目通过总结木桩桥木桩打设和上部结构施工过程中的难点与经验,重点研究形成一套关于木质桥梁安装的系统性技术总结,使工程在保证安全质量的前提下,达到缩短工期,降低成本的效果,为公司后期类似施工提供参考。
The Saudi Jubail Seashore Park Project summarized the difficulties and experience in the installation of the timber pile and timber bridge upper structure,and focused on the formation of a set of systematic technologies for the installation of the timber bridge,so that the project can guarantee the safety and quality of the project.It can shorten the construction period and reduce the cost,providing reference for similar construction in the later stage of the company.
作者
陈立庆
李启宁
CHEN Li-qing;LI Qi-ning(No.2 Engineering Company Ltd.of CCCC First Harbor Engineering Company Ltd.,Qingdao 266071,China)
出处
《价值工程》
2020年第8期132-136,共5页
Value Engineering
关键词
木质桥梁
木桩
系统性技术总结
timber bridge
timber pile