城市地铁长枕式无砟轨道直铺法施工工艺 被引量:1

Construction Technology of Direct Laying Method for Long Sleeper Ballastless Track of Urban Subway
下载PDF
导出
摘要 马来西亚地铁2号线道床结构特殊,含防脱轨墙,并且该道床采用了2.2m的混凝土轨枕。道床施工顺序为自上而下,先组装轨排,后安装钢筋模板浇筑混凝土。优点是闪光焊及道床施工等大部分工作利用桥面极大地减少了临时用地,同时,设计的轨排架模板系统结构简洁适合防脱轨墙特殊结构道床。 The track bed of Malaysia metro line 2 has special structure, including anti-derailment wall, and the track bed adopts 2.2 m concrete sleeper. The construction sequence of the track bed is from top to bottom, first the track bar is assembled, and then the steel bar formwork is installed to pour concrete. The advantage is that most of the work, such as flash welding and road bed construction, has greatly reduced the use of temporary land. At the same time, the design of the track rack formwork system structure is simple and suitable for the special structure of anti-derailment wall track bed.
作者 张文军 史炳峰 陈建 张学超 ZHANG Wen-jun;SHI Bing-feng;CHEN Jian;ZHANG Xue-chao(CCCC-SHEC Railway Engineering Co.Ltd.,Xi'an 710065,China)
出处 《工程建设与设计》 2020年第6期79-81,共3页 Construction & Design for Engineering
关键词 防脱轨墙 轨排架 长轨枕 derailment wall section of track long sleeper
  • 相关文献

参考文献1

二级参考文献4

共引文献1

同被引文献3

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部