摘要
介绍了巴基斯坦卡洛特水电站的工程概况,针对该项目软岩筑坝、软岩洞室群稳定、地震烈度高、泥沙含量高等技术难题,通过现场试验研究、室内试验研究及模型分析等手段,以及借鉴类似项目的成功经验,提出了针对卡洛特项目各技术难题的实际解决方案,为工程建设提供了技术支撑。
This paper describes the engineering overview of Karot Hydropower Project in Pakistan.Aiming at the technical issues of soft rock fill dam,the stability of soft rock caves group,high seismic intensity,higher sediment content etc.,the practical solutions are put forward through the indoor test research,field experimental research and model analysis,as well as successful experiences from the similar projects.The method can provide technical supports for the project construction.
作者
鄢双红
YAN Shuanghong(Changjiang Survey,Planning,Design and Research Co.,Ltd.,Wuhan 430010,China)
出处
《水利水电快报》
2020年第1期36-41,共6页
Express Water Resources & Hydropower Information
关键词
沥青混凝土心墙堆石坝
施工导流
泄洪消能
卡洛特水电站
asphalt concrete core wall rockfill dam
construction diversion
flood discharge energy dissipation
Karot Hydropower Project