摘要
结合包西线牵引供电设施改造工程施工实践,分析既有接触网七跨分相改八跨分相深层次原因,针对包西线客货运行情况,明确改造施工范围,提出可行的改造施工方案,并对改造施工方案的优势及创新点进行分析,全面总结了施工经验,希望为类似工程提供参考。
With reference of construction practices for reconstruction project of traction power supply facilities of Baotou-Xi’an railway,the paper analyzes the underlying causes for modification of existed OCS 7-span neutral section into 8-span neutral section,and with regard to the passenger and freight traffic status on Baotou-Xi’an railway,defines clearly the reconstruction scope,proposes the feasible reconstruction scheme,analyzes its advantages and innovation points,summarizes thoroughly the construction experience,hoping to provide references for the similar projects in the future.
出处
《电气化铁道》
2020年第1期81-84,共4页
Electric Railway
关键词
接触网
分相改造
三机重联
OCS
reconstruction of neutral section
three-locomotive operation