汽轮机在火力发电中起到能量转换作用,汽轮机本体安全正常,电力生产要求的机械能才可以不停地获得供给。汽轮机本身具有强烈的系统性,在使用之前,要求有关人员把组装完成的汽轮机机组安装有效落实。在安装施工的时候,也许会遇到位置的转换和安装错误等问题,这类问题和安装施工工艺质量有直接联系,有关人员还需要由施工工艺着手,对它开展管理,从而加强汽轮机的运转效率和使用年限。
Steam turbines have an energy conversion function in thermal power generation.The steam turbines were originally safe and normal,and the mechanical energy required for power production could be continuously supplied.The steam turbine itself has a strong systemic nature.Before use,relevant personnel are required to effectively implement the assembled steam turbine unit.During installation and construction,you may encounter problems such as location conversion and installation errors.Such problems are directly related to the quality of the installation and construction process.The relevant personnel also need to start with the construction process and manage it to strengthen the operation of the turbine Effi ciency and useful life.
作者
黄士家
黄士愿
刘霏
Huang Shi-jia;Huang Shi-yuan;Liu Fei
出处
《电力系统装备》
2020年第1期57-58,共2页
Electric Power System Equipment
关键词
火电厂
汽轮机本体
安装施工工艺
thermal power plant
turbine body
installation and construction technology