摘要
本文通过采取对塑料排水板打设机械设备的改装、增加有效装置以及改进施工工艺等一系列施工控制措施后,攻克了塑料排水板在复杂地层打设不成功的难题,加快了施工进度,积累了施工经验,取得了显著的经济效益和社会效益,为类似工程提供了可移植性参考。
The construction of plastic drain band in complex stratum is successfully completed by modifying equipment,adding effective devices and improving construction technology.The above series of construction control measures are used to speed up the construction progress,accumulate the construction experience and achieve significant economic and social benefits,which will provide a reference for similar projects.
作者
郭东
邢荣亮
王瑞
Guo Dong;Xing Rongliang;Wang Rui(Tianjin Deep Foundation Engineering Co.,Ltd.,Tianjin 300222,China)
出处
《港工技术》
2020年第2期53-56,共4页
Port Engineering Technology
关键词
塑料排水板
复杂地层
回带
plastic drain band
complex stratum
band return