沙沱升船机双向桥机安装技术 被引量:1

Two-way Bridge Crane Installation Technology of Shatuo Ship Lift
下载PDF
导出
摘要 沙沱升船机主机房布置1台1250/2×150kN双向桥机,主桥架长37m。受限于沙沱水电站运输条件,桥架采用厂内分段制造、现场拼装的安装方式。文章将详细介绍升船机双向桥机的吊装、安装和负载试验,以期为今后升船机大型桥式起重机安装、调试提供经验。 The main machine room of the Shatuo ship lift is equipped with a 1250/2 x150 kN two-way bridge crane. The length of the main bridge is 37 m, which is limited to the transportation conditions of the shatuo hydropower station. The bridge is made in sections in the factory and assembled on site.This paper introduces in detail the hoisting, installation and load test of the ship lift twoway bridge cranes, providing experience for the installation and commissioning of the ship lift large bridge cranes in the future.
作者 王敏 李倩 黄金根 WANG Min;LI Qian;HUANG Jingen(Hangzhou Guodian Machinery Design and Research Institute Co.,Ltd.,Hangzhou 310030)
出处 《现代制造技术与装备》 2020年第1期168-169,共2页 Modern Manufacturing Technology and Equipment
关键词 沙沱升船机 双向桥机 安装 调试 shituo ship lift two-way bridge crane installation debugging
  • 相关文献

参考文献2

共引文献3

同被引文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部