摘要
本文以市政连续钢箱梁桥为研究对象,分析了钢箱梁桥节段吊装施工控制问题,明确了吊装施工的具体环节和流程,辨识出吊装施工过程中的重点环节,希望对后续的钢箱梁节段吊装施工提供参考。
Taking municipal continuous steel box girder bridge as the research object,this paper analyses the segment hoisting and erection of steel box girder bridge.This paper clarifies the specific links and processes of hoisting construction,identifies the key links in the process of hoisting construction,and hopes to provide reference for subsequent steel box girder segment hoisting construction.
作者
任锦明
REN JinMing(Jinzhong Agent Construction Management Service Center,Jinzhong 030600,China)
出处
《四川建材》
2020年第4期87-88,共2页
Sichuan Building Materials
关键词
钢箱梁桥
节段吊装
施工控制
steel box girder bridge
segment hoisting
construction control