某超长剪力墙结构温度应力计算及控制

Calculation and Control of Temperature Stress in Large Horizontal Length Shear Wall Structure
下载PDF
导出
摘要 文章通过确定混凝土结构的温差数值,经对比计算施工阶段和正常使用阶段的温差,结果表明施工工况为降温的控制工况,采用有限元计算超长结构施工阶段温度应力分布;计算结果表明,楼板在温度作用下的拉应力以长度中心线为基准沿长度方向扩展,在楼板凹角、洞口及竖向构件处出现应力集中,2层楼面为温度应力影响最大的楼层;合理的温差取值是温度应力计算的前提。 The value of temperature difference of concrete structure is discussed in this paper, Comparison of the temperature difference between construction stage and service stage is carried. As the result the construction state is the Control Status, FEA method is used in Calculating the distribution of temperature stress.The results shows that the tensile stress of the slab under the temperature action,which extension along the length of building is based on the centerline of the length. stress concentration occurs at the concave corner and the hole of floor and even occurs at the shear wall.the maximum thermal stress occurs at the second floor of the building;especially, the reasonable value of the temperature difference is the precondition of the thermal stresses analysis.
作者 董贺勋 施建波 陈佳佳 DONG He-xun;SHI Jian-bo;CHEN Jia-jia(Institute of Architectural Design and Planning Co.,Ltd of Nanjing University,Nanjing Jiangsu 210000 China)
出处 《江苏建筑》 2020年第1期44-46,共3页 Jiangsu Construction
关键词 超长剪力墙结构 温差 施工管理 large horizontal length shear wall structure temperature difference construction management
  • 相关文献

参考文献3

二级参考文献16

  • 1范重,王大庆,唐杰,尤天直,毕磊,王春光.唐山国际会展中心超长大跨度预应力结构设计[J].建筑结构,2006,36(1):56-63. 被引量:16
  • 2游宝坤 陈富银 等.UEA水泥沙浆与混凝土长期性能的研究.第二届全国混凝土膨胀剂学术交流会论文集[M].北京:中国建材工业出版社,1998..
  • 3韩重庆.大面积预应力混凝土梁板结构不设温度缝研究[M].东南大学,2001..
  • 4韩重庆,学位论文,2001年
  • 5过镇海,钢筋混凝土原理,1999年
  • 6王铁梦,工程结构裂缝控制,1997年
  • 7周履,收缩徐变,1994年
  • 8GB J10 89 混凝土结构设计规范
  • 9游宝坤,第二届全国混凝土膨胀剂学术交流会论文集,1998年
  • 10傅学怡,吴兵.混凝土结构温差收缩效应分析计算[J].土木工程学报,2007,40(10):50-59. 被引量:76