摘要
以BIM技术在郑万铁路赵河镇跨南水北调特大桥施工中的应用为例,阐述了BIM技术在二维图纸工程量审核,钢筋排布,复杂构件钢筋下料应用中给施工管理带来的明显提升。同时利用BIM5D平台技术提高进度管理的水平,BIM5D移动端的使用,可加大现场质量、安全的管控能力。
Taking some sections of Zhengzhou Wanzhou railway as an example,this paper expounds how to use BIM Technology to solve the problems such as the difficulty in checking the quantities of two dimensional drawings,the unreasonable arrangement of steel bars,and the inaccurate blanking of steel bars for complex components.At the same time,BIM 5d platform is used to solve the problem of schedule management,and BIM 5d mobile terminal is used intensively to enhance the management and control ability of site quality and safety.
作者
仲福增
ZHONG Fuzeng(China Railway 15th Bureau Group No.5 Engineering Co.,Ltd.,Tianjin 300133,China)
出处
《工程质量》
2020年第3期41-43,54,共4页
Construction Quality
关键词
郑万铁路
BIM技术
进度管理
Zhengzhou Wanzhou railway
BIM technology
progress management