巴音沟河渠首泄洪闸冲刷模型试验研究 被引量:4

Experimental Study on Owerflow Capacity of Spillway Sluice at the Headwork of Bayingou River
下载PDF
导出
摘要 对拟除险加固的巴音沟河渠首引水枢纽开展水工模型冲刷试验。试验结果表明:设计洪水时(流量322m3/s)内库上坝(坝顶高程876.2m)坝前水面高程875.7m,较坝顶低0.5m,在校核洪水时,坝前水面高于坝顶出现漫溢,建议加高内库上坝高度;2种工况下冲刷坑基本趋于稳定。 The scour test of hydraulic model is carried out for the diversion project of bayingou river head to be reinforced. The test results show that the elevation of the water surface in front of the dam is 875.7 m, which is 0.5 m lower than the dam crest during the design flood(flow of 322 m3/s). During the check flood, the water surface in front of the dam is higher than the dam crest, so it is suggested to increase the height of the upper dam of the internal reservoir. Under the two conditions, the foundation of the scour pit tends to be stable.
作者 于旭永 YU Xu-yong(Survey and Design Institute(Group)Co.Ltd.,Shihezi 832000,China)
出处 《工程建设与设计》 2020年第7期143-145,共3页 Construction & Design for Engineering
关键词 巴音沟河 渠首 泄洪闸 冲刷 Bayingou river canal head flood discharge sluice scour
  • 相关文献

同被引文献19

引证文献4

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部