摘要
随着计算机控制技术的发展,桥梁钢塔转体是具有代表性的安装方法之一,具有安全、可靠,经济、工期短等优点,为了进一步提高加工精度,降低现场施工难度、缩短现场安装时间,转动铰及其上下节段在钢结构加工厂里面完成组装、试转工作。
With the development of computer control technology,the turning of bridge steel tower is one of the representative installation methods,which has the advantages of safety,reliability,economy,short construction period,etc.In order to further improve the processing accuracy,reduce the difficulty of site construction and shorten the installation time,The rotary hinge and its upper and lower segments are assembled and tested in a steel structure processing plant.
作者
杨学斌
李胜乾
周国庆
张银国
张西杰
Yang Xue-bin;Li Sheng-qian;Zhou Guo-qing;Zhang Yin-guo;Zhang Xi-jie
出处
《建筑技术开发》
2020年第2期98-99,共2页
Building Technology Development
关键词
钢塔
转体施工
转动较
试转
steel tower
rotation construction
rotation comparison
trial rotation