摘要
结合广州某超高层项目的结构设计,对全逆作法的支护结构、竖向支撑系统、梁柱连接节点等设计全过程阐述,从而解决了施工场地狭小、施工周期紧张的问题,为同类型工程的结构设计提供参考。
Combined with the structural design of a super high-rise building project in Guangzhou,the whole design process of the supporting structure,vertical support system,beam column connection nodes and so on is described,so as to solve the problems of narrow construction site and tight construction period,and provide reference for the structural design of the same type of project.
作者
朱祖敬
赵松林
程炜
吕鹏
Zhu Zujing;Zhao Songlin;Cheng Wei;Lv Peng(Guangzhou Design Institute Guangzhou 510620,China)
出处
《广东土木与建筑》
2020年第4期13-17,共5页
Guangdong Architecture Civil Engineering
关键词
全逆作法
逆作结构选型
出土方案
逆作工序
地下室结构设计
full reverse method construction
type selection of reverse construction structure
excavation plan
reverse working procedure
basement structure design