摘要 为解决盾构隧道在全断面砂层中下穿高层建筑物难以控制地面沉降并可能引发建筑物安全风险的问题,以南昌地铁2号线盾构施工下穿既有建筑物工程案例为依托,采用数值模拟计算,研究采取措施的必要性,并据此提出斜向注浆加固技术,同时根据现场监测数据,研究注浆加固效果。研究认为,采用注浆加固措施有较大的实施意义,能够有效减少建筑物所受盾构下穿过程中土体扰动的影响,能够满足相关施工规范要求,可对今后的工程提供有意义的参考。 In order to solve the problem that it is difficult to control ground subsidence and possibly lead to building safety risk when shield tunnel passes through high-rise buildings in full-face sand layer,the paper is based on the case of shield tunneling under existing buildings of Nanchang Metro Line 2,using numerical simulation to study the necessity of taking measures.Based on this,oblique grouting reinforcement technology is put forward.At the same time,grouting reinforcement effect is studied according to field monitoring data.It is concluded that the grouting reinforcement measures are of great practical significance,can effectively reduce the influence of soil disturbance during the shield tunneling process,can meet the requirements of relevant construction codes,and can provide meaningful reference for future projects.
作者 罗文静 Luo Wenjing(Guangzhou Metro Design&Research Institute Co.,Ltd.Guangzhou 510010,China)
出处 《广东土木与建筑》 2020年第4期39-41,94,共4页 Guangdong Architecture Civil Engineering
关键词 盾构隧道 下穿建筑物 注浆加固 数值模拟 沉降分析 shield tunnel underpass buildings grouting reinforcement numerical simulation settlement analysis
  • 相关文献

参考文献7

二级参考文献55

共引文献348

同被引文献27

引证文献4

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部