短钢板桩围堰+管井降水干封混凝土施工技术研究 被引量:1

Research on Construction Technology of Short-steel Steel Sheet Pile Cofferdam+Pipe Well Dewatering Dry Sealing
下载PDF
导出
摘要 钢板桩围堰是桥梁基础施工最重要的临时结构,传统深基坑施工工艺主要是采用钢板桩围堰+水下吸泥的方式。而官渡黄河大桥项目根据黄河滩地富水砂层的地质特点进行创新,即采用钢板桩围堰+管井降水的施工工艺,围堰内取土采用长臂挖机+高压射水、泥浆泵吸泥的施工方式,实现围堰内部干燥作业环境,提高了工作效率,加快了施工进度,保证了施工安全可靠。 Steel sheet pile cofferdam is the most important temporary structure for bridge foundation construction.Traditional deep foundation pit construction technology mainly uses steel sheet pile cofferdam+underwater mud suction.The Guandu Yellow River Bridge project is innovated according to the geological characteristics of the water-rich sandy layer of the Yellow River beach land,that is,the construction process of steel sheet pile cofferdam+pipe well precipitation,and the inside of the cofferdam uses long arm excavator+high pressure water jet,mud pump suction the construction method realizes the dry working environment inside the cofferdam,improves the work efficiency,speeds up the construction progress,and ensures the safety and reliability of the construction.
作者 张凌云 Zhang Ling-yun
出处 《建筑技术开发》 2020年第4期46-48,共3页 Building Technology Development
关键词 钢板桩围堰 管井降水 混凝土干封 steel sheet pile cofferdam pipe well precipitation concrete dry seal
  • 相关文献

参考文献1

二级参考文献3

  • 1地基与基础施工手册.中国建筑工业出版社,1997.
  • 2土力学基础与基础.武汉工业大学出版社,1993.
  • 3深基础施工挡土支护技术.冶金建筑研究总院情报室,1987.

共引文献1

同被引文献1

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部