为研制灌注桩基础施工的多功能履带式钻吊一体机,提出了总体结构方案。同时,对吊装结构进行了优化,包括尺寸优化、拓扑优化和形状优化等,并提出了新型钻吊结合部位结构,以为类似工程提供借鉴。
A multi-functional drilling and lifting integrated machine on track chassis was developed for the routing pile foundation construction.At the same time,the lifting structure was optimized,including size optimization,topology optimization,shape optimization,etc.,and a new type of drilling-hanging joint structure was proposed to provide reference for similar projects.
作者
夏睿
徐铼
高歌
邵腾飞
舒邦京
Xia Rui;Xu Lai;Gao Ge;Shao Teng-fei;Shu Bang-jing
出处
《建筑技术开发》
2019年第24期1-2,共2页
Building Technology Development
关键词
钻吊一体机
灌注桩
结构优化
drilling and lifting integrated machine
cast-in-place pile