上跨铁路既有线关键架梁技术探析 被引量:2

Key Beam Erecting Technology of the Existing Railway
下载PDF
导出
摘要 结合某铁路桥跨既有线架梁施工,根据架桥机和梁板自重、架桥机架梁高程确定承重混凝土基础尺寸,并对架桥机过孔、梁板架设施工工艺及所需时间进行分析、总结规律,进一步规范架桥机上跨铁路施工程序。 Combined with the construction of a railway bridge across the existing line,the size of bearing concrete foundation is determined according to the self-weight of the bridge erecting machine and the beam slab and the elevation of the bridge erecting frame beam.Through the analysis of the construction technology and the time required for the bridge erecting machine moving through the hole and the beam slab erection,the construction procedure of the bridge erecting machine on the broken iron road is standardized.
作者 耿永征 GENG Yong-zheng(The 2nd Engineering Co.,Ltd.of China Railway 18th Bureau Group,Tangshan,Hebei 064000,China)
出处 《广东水利电力职业技术学院学报》 2020年第1期16-19,共4页 Journal of Guangdong Polytechnic of Water Resources and Electric Engineering
关键词 跨既有线 架梁 施工程序 across existing lines beam erecting construction procedure
  • 相关文献

参考文献4

二级参考文献2

  • 1TB 10002.5-2005,铁路桥涵地基和基础设计规范[S].
  • 2TB10002.2-2005,铁路桥梁钢结构设计规范[S].

共引文献15

同被引文献17

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部